Footing Inspection
To be made after excavations are complete and include form work and reinforcing steel as required. Soil tests and engineer reports may be required on projects where soil conditions are less than ideal.
Foundation Wall Inspection
For concrete, all materials for the wall are to be in place including prepped reinforcing, form work and any engineering documentation if required by the building department. No inspections are required for short walls under (4'-0) four feet. For treated wood, additional inspections may be required.
Underslab
To be made after all under floor or in slab service equipment, conduit, piping, plumbing, or other equipment items are in place before pouring concrete.
Permanent Or Temporary Electric Service
Includes meter base, main breaker panel or disconnect (if required) and two ground rods. Call 668-1000x1250 for more information. If approved by the building department we inform one of the four power companies that serve our county. It is then the responsibility of the owner to set up an account and schedule the connection with the power company.
Rough In Inspections
Plumbing, mechanical and electrical inspections are to be made prior to insulation or any covering or concealment of pipes, wires, vents or ductwork and can be with the framing inspection.
Plumbing
Includes all water, waste and vent lines installed, properly supported and protected with nail guards as needed.
Mechanical
Includes all gas lines, heating ducts or piping, bathroom exhaust venting, furnace, fireplace and water heater venting.
Electrical
Includes all wires pulled into properly sized junction boxes with wire stripped and grounds bonded ready for devices.
Framing Inspection
To be made after completion of walls, roof, floor system, sheathing, stairs, windows, exterior doors, fire blocking.
Final Inspection
To be made after all inspections are complete and then a certificate of occupancy will be issued when the final inspection is approved.