CR 200 N Roadway Reconstruction
CR 200 N Roadway Reconstruction Project
Location: CR 200 N from City Limits to SR 827
Designed By: American Structurepoint
Inspected By: To be determined
Contractor: To be determined
Estimated Construction: Estimated Completion:
Begin Date: Summer 2017 End Date: Summer 2019
Estimated Cost: $3.5 million Funded By: Federal Funds 80%
Local Funds 20%
Steuben County and the City of Angola are teaming on this project which proposes widening the roadway to include two 12-foot travel lanes with 10-foot shoulders (4-foot paved and 1-foot gravel) and provide open side ditches. The at-grade railroad crossing along this corridor will also be widened and improved to include additional safety measures. The total length of improvements is approximately 3,060 feet.